GENERAL
In the execution of its mandate
to provide adequate and reliable electric power to the nation at economically
reasonable tariff, the Liberia Electricity Corporation
(LEC) operates and maintains two (2) distinct electrical power system,
namely: the Monrovia Power system and the rural Electrification system. The
Monrovia
power system before the war supplied electricity to
Monrovia
and its outlying areas, extending to
Kakata
City
, Tubmanburg City, and
Buchanan
City
. Rural electrification before the war operated eleven (11) isolated
diesel out stations with three under construction at the onset of the civil war,
served the people who resided out side the Monrovia
power system.
THE EVOLUTION OF LEC
In the early 1940s, the Monrovia
Power system consisting of a single unit, serving the public. The unit was
located at the corner of Carey & Lynch streets and was operated by Henry F.
Luke, after whom the Luke Power plant at
Bushrod
Island
is named. Monthly collection then never exceeded 16% of the monthly billing.
In the year 1949, the Government
of Liberia (GOL) procured three 40-kW superior diesel generators through the
United States Government Land Lease Program, and installed them at the Krutown
power plant where the LEC central office is located today.
The Liberian company led by
Commander William R. Trimble under contract with the GOL, replaced the Liberia
Company and operated the Krutown power plant until 1960.
In June 1960, the Monrovia Power
Authority (PUA) was created by law to consolidate and control the activities
associated with power generation, transmission and distribution with the view to
reducing system technical and commercial losses. The Stanley Engineering Company
was hired by the GOL to manage the MPA. However, in 1964 Sanderson and Porter
replaced
Stanley
engineering company. The GOL at the time preferred
Stanley
engineering company to carrying out the task of surveying, designing and
supervising the Mount Coffee Hydroelectric project.
In 1962, the national
Legislature pass an act to amend the one that created the MPA, thereby creating
the Public utility Authority (PUA). The act creating the PUA transferred to the
PUA, the Division of water and sewer from the Department of Public works,
Telecommunication and Broad casting. The Government of Liberia (GOL) secured a
loan in 1963 an IDA World Bank loan of US$ 24.3million to construct a 34 MW
hydroelectric station on the
St. Paul
River
.
Raymond concrete pile Company,
Orby Construction Company and the Schulman-Mass Gen J.V. Began in 1964,
respectively, the construction of hydro station associated transmission
facilities and substation. Upon completion in 1967, the hydropower plant was
dedicated as the T. J. R. Faulkner W.F. Walker Hydroelectric Power Station which
is situated in
Harrisburg
.
On July 12, 1973, by an act of
National legislature, the Liberia Electricity Corporation was formerly
established with the mandate to plan generate transmit and distribute electric
energy throughout the length and breadth of the
Republic
of
Liberia
. The LEC came into official business on October 11, 1976, following the
printing of the act into handbill by GOL.
THE
MONROVIA
POWER SYSTEM
The LEC pre-war power system
consisted of hydro and thermal generating facilities with a combined installed
capacity of 182MW. The Mount Coffee Hydro Power Plant accounted for 64MW and
thermal power plant consisted of Gas Turbines Plants. The slow speed diesel
(Luke Power Plant) and the medium speed diesel (Bushrod Plant) contributed 68MW,
40MW, and 10MW respectively. The average annual energy production of these
plants stood at 435GWh in 1989
The transmission and
distribution facilities consisted of ten (10) manned and six unmanned substation
with a combined install transformer capacity of 260MVA. The transformer network
consisted of double and single circuit 69-kV lines that spanned about 460km
strung on a wooden pole, lattice steel tower and tubular steel poles
and extended 45km northeast of
Kakata city, 29km northwest of
Tubmanburg and 121km northwest to the city of
Buchanan
while the distribution network consisted of approximately 800km of 12.5 kV
overhead and underground circuits. All of these facilities were virtually
damaged during and after the civil war.
With all of the LEC facilities
damaged as a results of war, it became appropriate to effect the long awaited
power system change, over which the years left Liberia as the only Country in
Africa that operated power system base on North America standard of 60htz
, 220/110v customer voltage.
In 1998, with funding with from
the Danish Development Agency (DANIDA), a Danish Consulting firm NESA Team,
carried out a power system conversion study. Today,
Liberia
has effectively converted its system from the
North America
standard to 50HTz 400/230V customer voltage.
In 2000, a Taiwanese grant
of 2.4M, was given to install a7MW of power in Bushrod yard. This 7MW of power
was taken out of service in 2004, due to mechanical/electrical problems and lack
of spare parts.
RURAL ELECTRIFICATION
The Government of
Liberia
owned the Rural Electrification System. The development of rural electrification
dates as far back as 1945, when four individual power stations with
a total installed capacity of 800kW were constructed in Robertsports,
Grand Cape Mount County; Buchanan, Grand Bassa County; Greenville Sinoe County
and Harper Maryland County.
In 1966, another station was
built in Saniquille,
Nimba
County
and in 1968, becoming the first outstation.
The rural electrification
program formerly established in 1978, when the Government of Liberia (GOL)
obtained a loan to purchase and install 15 Mirrlees Blackstone diesel generators
set with a total installed capacity of 13MW. These generator facilities along
with the associated distribution networks and customers service connection were
destroyed during the civil war.
Eleven (11) outstations were
established before the war, while another three were under construction at the
onset of the war. The rural electrification system had before the war 90 miles
of 12,5kV three phase and 7.2 kV single phase distribution lines and 26 miles of
low voltage service lines, about 570 distribution transformers and more that
1700 wooden pole. At the outbreak of the civil war, the total number of
customers connection as grown up to about 9,000 of which the Gbarnga outstation
was by far the largest with 2,500. The rural Electrification System served the
people in 11 population centers in rural
Liberia
.
The rural electrification system
was not completely successful due to a number of factors including high
maintenance cost, low tariffs, consumers failure to pay , inadequate
and delayed subsidies from GOL as well as endemic overstaffing.
Although the commercial
profitability was minimum, the socio-economic benefits to rural dwellers were
enormous, which in any case the significant justification for rural
electrification.
LEC PRESENT STATUS
Since Her Excellency Madam Ellen
Johnson Sirleafe’s
as President of the
Republic
of
Liberia
, during the October 2005 General and Presidential elections, and in fulfillment
of campaign promise to provide electricity to parts of
Monrovia
, and its environs, the pace was set for the Emergency Power Program (EPP) for
Monrovia
Accordingly, on March 31, 2006,
a Memorandum of Understanding (MOU) was signed and entered into by the European
Commission (EC) in
Liberia
, the Government of the
United States of America
, through USAID, the government of
Ghana
through the Volta River Authority (VRA) and Government of the
Republic
of
Liberia
, for the implementation of the Emergency power program for
Monrovia
.
GENERATION
The Emergency Power Program EPP
basically involved the installation of two 1250kVA diesel generators and two
400KVA diesel generators in both
Congo
Town
,
Kru
Town
. To date only two (2) of the diesel power generators (1250kVA gensets) have
been installed and commissioned on July 26, and September 15, 2006 in
Congo
Town
and
Kru
Town
, respectively. The total combined install capacity of the two units is 2,
5000kVA.
The
Congo
Town
and
Kru
Town
power plant operated for 159 and 107 days respectively in 2006.
ENERGY PRODUCTION CHART
Congo
Town
Power Plant
|
NO
|
Month
|
Energy Produced (kWh)
|
|
1
|
July
|
31,326
|
|
2
|
August
|
146,283
|
|
3
|
September
|
177,085
|
|
4
|
October
|
206,005
|
|
5
|
November
|
254,854
|
|
6
|
December
|
283,095
|
|
|
TOTAL
|
1,098,648
|
ENERGY PRODUCTION CHART
Kru Town Power plant
|
NO
|
Month
|
Energy Produced (kWh)
|
|
1
|
July
|
0
|
|
2
|
August
|
0
|
|
3
|
September
|
24,041
|
|
4
|
October
|
196,555
|
|
5
|
November
|
329, 170
|
|
6
|
December
|
397,230
|
|
|
TOTAL
|
946,996
|
The combined gross energy produced by both Congo Town and Kru Town
Power Plants under the EPP-I for the period under review is 2, 045,644.
The Emergency Power
Program for
Monrovia
has had limited generating capacity. To supplement EPP-I, EPP –II has
been envisaged to expand the project by installing two diesel generators
in Paynesville to cover a total distance of 8km of low voltage for
streetlights.
Also four more diesel generators
will be installed in
Kru
Town
, with the transfer and installation of the present EC funded generators
at
Kru
Town
to
Congo
Town
to increase the generation capacity within Congo Town Project zone.
Furthermore, two diesel generators will be installed at Bushrod and to expand the MV/LV
network
TRANSMISSION AND
DISTRIBUTION
The distribution network
consisting of 12km of medium voltage (MV) and 18km of low voltage (
LV
) network have been constructed and commissioned; spanning parts of
Congo
Town
/ Sinkor and Central Monrovia/West Point under EPP-I with 430 streetlights
installed.
Under the European
Commission grant aid, three transmissions substation were rehabilited in
Kru
Town
, Capitol and Paynesville.
COMMERCIAL ACTIVITIES
The LEC depends on the
energy it supply its customers and how efficiently the energy flows is
monitor, billed and transformed into collected revenue.
Predicated upon these
conditions, under EPP-I, the LEC Management in collaboration with the IRG/USAID
has put into place a number of measures aimed at enhancing billing and
collection efficiency as well as minimizing system loses. In this regards,
a Metering Billing and Collection (MBC) system was put into place.
In 2006, the total number
of 340 customers of various categories, namely, schools, hospitals,,
clinics, residential, businesses and Public facilities have been connected
to the EPP-I grid.
ENERGY
SALE
CHART
Congo
Town
Power Plant
|
NO
|
Month
|
Energy Billed (kWh)
|
Energy charged (USD)
|
Collection (USD)
|
|
1
|
July
|
O
|
O
|
O
|
|
2
|
August
|
112185
|
48,763.00
|
4,175.00
|
|
3
|
September
|
150,641
|
66,305.00
|
21,478.00
|
|
4
|
October
|
164,085
|
72,659.00
|
30,437.00
|
|
5
|
November
|
205,139
|
72,567.00
|
128,080.00
|
|
6
|
December
|
285700
|
97,138.00
|
49,976.00
|
|
|
TOTAL
|
917,750
|
357,432.00
|
234,146.00
|
ENERGY
SALE
CHART
Kru
Town
Power Plant
|
NO
|
Month
|
Energy Billed (kWh)
|
Energy charged (USD)
|
Collection (USD)
|
|
1
|
July
|
0
|
0
|
0
|
|
2
|
August
|
0
|
0
|
0
|
|
3
|
September
|
14596
|
6,380.00
|
1,550.00
|
|
4
|
October
|
118,736
|
53,853.00
|
23,019.00
|
|
5
|
November
|
240,125
|
8,6780.00
|
76,923.00
|
|
6
|
December
|
348,276
|
118,414.00
|
87,498.00
|
|
|
TOTAL
|
721,735
|
265,431.00
|
188,990.00
|
The Combined total energy billed is 1,639,485kWh, amounting to a
dollar value of USD$ 622,863.00, including GOL bills
The combined total payment
made by all customers’ amounts to US$ 423,136.00 representing 68%
collection efficiency.
PERSONNEL
The
present workforce of the LEC stands at 83, employees. This was possible by
Government’s
US
$500.000.00 provision which successfully facilitated the downsizing
exercise here at the LEC
During the period under
review, there were four new appointments and two dismissals made in
Management, while a total number of three employees lost their lives. We
wish to express our heartfelt condolence to the bereaved family.